J-0081
acceptedAccept- Line
- LN-12
- Station
- 48+60
- Weld date
- 2026-05-04
- Spec
- 24" × 0.375"
31.84941, -102.39536
No open cross-check alerts on this joint.
Welder passes
- RootWorking sideWeston Trahan RC-133
May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideJunior Escamilla RC-158
May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideLuis Ontiveros RC-231
May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideJesse Karr RC-455
May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillWorking sideAndre Pickett RC-412
May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideAndre Pickett RC-412
May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideSam Whitfield RC-388
May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 4, 2026, 8:00 PM · P. Estrada (ASNT II)
No recordable indications.
RT film map — clock position1 indication12123456789101112- LCLow cap1:14–1:17 · 0.22" · d 0.03"Call varies by inspectorMinor indication, within acceptance limits.
Visual inspection (CWI)
API 1104 · Root bead visual prior to hot pass.
API 1104
Coating inspection
- DFT
- 26.1 mils
- Holidays
- 0
- Surface temp
- 90°F
- Humidity
- 41%
SSPC-SP 10 near-white blast · FBE + ARO overlay