J-2500
acceptedAccept- Line
- LN-12
- Station
- 1500+00
- Weld date
- 2026-05-29
- Spec
- 24" × 0.375"
33.32500, -103.75000
Cross-check alerts
Timing conflict
Inspection timestamp precedes the final welding pass on this joint.
NDT shot before visual inspection
Radiography was shot before the CWI visual inspection was completed - inspection sequence out of order.
Welder passes
- RootDitch sideWeston Trahan RC-133
May 29, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootWorking sideDwayne Ferris RC-204
May 29, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideJunior Escamilla RC-158
May 29, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideHector Ruiz RC-528
May 29, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideJesse Karr RC-455
May 29, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillWorking sideSam Whitfield RC-388
May 29, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- CapDitch sideCody Latham RC-165
May 29, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideDale Whitcomb RC-533
May 29, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
NDT results
- RTAccept
May 29, 2026, 5:00 AM · D. Halloran (ASNT II)
No recordable indications.
RT film map — clock position0 indicationsClean film — no recordable indications12123456789101112
Visual inspection (CWI)
API 1104 · Bevel, alignment and hi-lo verified prior to root.
API 1104
Coating inspection
No coating inspection recorded for this joint.