J-0013
acceptedAccept- Line
- LN-12
- Station
- 7+80
- Weld date
- 2026-05-04
- Spec
- 24" × 0.375"
31.80793, -102.35728
No open cross-check alerts on this joint.
Welder passes
- RootWorking sideOdell Rains RC-121
May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideTravis Nolan RC-307
May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideLuis Ontiveros RC-231
May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillWorking sideAndre Pickett RC-412
May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillDitch sideSam Whitfield RC-388
May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- CapWorking sideRonnie Pace RC-547
May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideKelly Boudreaux RC-350
May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 4, 2026, 8:00 PM · P. Estrada (ASNT II)
No recordable indications.
RT film map — clock position1 indication12123456789101112- EUExcess reinforcement10:07–10:11 · 0.42" · d 0.06"Minor indication, within acceptance limits.
Visual inspection (CWI)
API 1104 · Bevel, alignment and hi-lo verified prior to root.
API 1104 · Root bead visual prior to hot pass.
API 1104
Coating inspection
- DFT
- 18.6 mils
- Holidays
- 0
- Surface temp
- 89°F
- Humidity
- 39%
SSPC-SP 10 near-white blast · FBE + ARO overlay