J-1096
acceptedAccept- Line
- LN-12
- Station
- 657+60
- Weld date
- 2026-05-15
- Spec
- 24" × 0.375"
32.46856, -102.96376
Cross-check alerts
No CWI visual inspection recorded
Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.
Welder passes
- RootDitch sideBrent Kessler RC-540
May 15, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootWorking sideDwayne Ferris RC-204
May 15, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideBo Kinchen RC-146
May 15, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideLuis Ontiveros RC-231
May 15, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillWorking sideKelly Boudreaux RC-350
May 15, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillDitch sideAndre Pickett RC-412
May 15, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideAndre Pickett RC-412
May 15, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideSam Whitfield RC-388
May 15, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 15, 2026, 8:00 PM · D. Halloran (ASNT II)
No recordable indications.
RT film map — clock position2 indications12123456789101112- PORPorosity12:03–12:05 · 0.20" · d 0.06"Minor indication, within acceptance limits.
- UCUndercut4:44–4:46 · 0.28" · d 0.01"Minor indication, within acceptance limits.
Visual inspection (CWI)
No visual inspection recorded for this joint.
No final visual on record — API 1104 requires a visual inspection on every weld.
Coating inspection
No coating inspection recorded for this joint.