WeldGuard
All joints

J-2746

acceptedAccept
Line
LN-12
Station
1647+60
Weld date
2026-06-01
Spec
24" × 0.375"

33.47506, -103.88776

Cross-check alerts

  • No CWI visual inspection recorded

    Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.

Welder passes

  1. RootWorking side
    Brent Kessler RC-540

    Jun 1, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  2. RootDitch side
    Dwayne Ferris RC-204

    Jun 1, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  3. Hot PassWorking side
    Travis Nolan RC-307

    Jun 1, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  4. Hot PassDitch side
    Hector Ruiz RC-528

    Jun 1, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  5. FillDitch side
    Shane Bergeron RC-181

    Jun 1, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  6. FillWorking side
    Dale Whitcomb RC-533

    Jun 1, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  7. CapDitch side
    Kelly Boudreaux RC-350

    Jun 1, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  8. CapWorking side
    Kelly Boudreaux RC-350

    Jun 1, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

NDT results

  • RTAccept

    Jun 1, 2026, 8:00 PM · D. Halloran (ASNT II)

    No recordable indications.

    RT film map — clock position1 indication
    12123456789101112
    • UCUndercut7:207:22 · 0.17" · d 0.06"Minor indication, within acceptance limits.

Visual inspection (CWI)

No visual inspection recorded for this joint.

No final visual on record — API 1104 requires a visual inspection on every weld.

Coating inspection

No coating inspection recorded for this joint.