J-0900
acceptedAccept- Line
- LN-12
- Station
- 540+00
- Weld date
- 2026-05-13
- Spec
- 24" × 0.375"
32.34900, -102.85400
No open cross-check alerts on this joint.
Welder passes
- RootWorking sideMarcus Cole RC-118
May 13, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
May 13, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideTravis Nolan RC-307
May 13, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideLuis Ontiveros RC-231
May 13, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillWorking sideKelly Boudreaux RC-350
May 13, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideSam Whitfield RC-388
May 13, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- CapDitch sideAndre Pickett RC-412
May 13, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideKelly Boudreaux RC-350
May 13, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 13, 2026, 8:00 PM · D. Halloran (ASNT II)
No recordable indications.
RT film map — clock position1 indication12123456789101112- SISlag inclusion5:38–5:40 · 0.25" · d 0.04"Minor indication, within acceptance limits.
Visual inspection (CWI)
API 1104
Coating inspection
- DFT
- 23.6 mils
- Holidays
- 0
- Surface temp
- 72°F
- Humidity
- 29%
SSPC-SP 10 near-white blast · FBE + ARO overlay
Call disputedOpen5/22/2026Dell Ramirez (Coating Sub Foreman) — DFT readings disputed — gauge calibration questioned, crew re-shot readings within spec range. Escalating to Level 3 coating inspector.
Escalated to Coating Level 3 · Rudy Tolentino (Coating Inspector Level 3)