J-0197
acceptedAccept- Line
- LN-12
- Station
- 118+20
- Weld date
- 2026-05-06
- Spec
- 24" × 0.375"
31.92017, -102.46032
No open cross-check alerts on this joint.
Welder passes
- RootDitch sideMarcus Cole RC-118
May 6, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootWorking sideDwayne Ferris RC-204
May 6, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideTy Maldonado RC-552
May 6, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideLuis Ontiveros RC-231
May 6, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillWorking sideRonnie Pace RC-547
May 6, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillDitch sideSam Whitfield RC-388
May 6, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- CapDitch sideKelly Boudreaux RC-350
May 6, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideKelly Boudreaux RC-350
May 6, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 6, 2026, 8:00 PM · P. Estrada (ASNT II)
No recordable indications.
RT film map — clock position2 indications12123456789101112- LCLow cap6:07–6:09 · 0.22" · d 0.09"Call varies by inspectorMinor indication, within acceptance limits.
- PORPorosity10:14–10:17 · 0.32" · d 0.02"Minor indication, within acceptance limits.
Visual inspection (CWI)
API 1104
Coating inspection
- DFT
- 20 mils
- Holidays
- 0
- Surface temp
- 63°F
- Humidity
- 44%
SSPC-SP 10 near-white blast · FBE + ARO overlay