WeldGuard
All joints

J-0059

acceptedAccept
Line
LN-12
Station
35+40
Weld date
2026-05-04
Spec
24" × 0.375"

31.83599, -102.38304

Cross-check alerts

  • Welder not qualified for this pipe spec

    Sam Whitfield welded the fill pass under WPS-1104-LH-04, which is qualified only to 16" OD — outside the 24" job spec. Weld requires re-work.

Welder passes

  1. RootWorking side
    Brent Kessler RC-540

    May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  2. RootDitch side
    Dwayne Ferris RC-204

    May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  3. Hot PassWorking side
    Ty Maldonado RC-552

    May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  4. Hot PassDitch side
    Luis Ontiveros RC-231

    May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  5. FillWorking side
    Kelly Boudreaux RC-350

    May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  6. FillDitch side
    Sam Whitfield RC-388

    May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-AG-07 Rev 1SMAW uphill 6G (fixed)E6010 / E7018

    2–12 in OD · wall 0.154–0.5 in · hardness 235 HV10 max

    Pipe 24" above WPS maximum 12"

  7. CapWorking side
    Kelly Boudreaux RC-350

    May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  8. CapDitch side
    Sam Whitfield RC-388

    May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

NDT results

  • RTAccept

    May 4, 2026, 8:00 PM · P. Estrada (ASNT II)

    No recordable indications.

    RT film map — clock position1 indication
    12123456789101112
    • SISlag inclusion4:254:27 · 0.20" · d 0.08"Minor indication, within acceptance limits.

Visual inspection (CWI)

  • Final visualAcceptHector SalasMay 4, 2026, 9:34 AM

    API 1104

Coating inspection

  • AcceptMarcus Ivey5/4/2026
    DFT
    21.3 mils
    Holidays
    0
    Surface temp
    94°F
    Humidity
    54%

    SSPC-SP 10 near-white blast · FBE + ARO overlay