J-0442
acceptedAccept- Line
- LN-12
- Station
- 265+20
- Weld date
- 2026-05-08
- Spec
- 24" × 0.375"
32.06962, -102.59752
Cross-check alerts
No CWI visual inspection recorded
Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.
Welder passes
- RootWorking sideWeston Trahan RC-133
May 8, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
May 8, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideTy Maldonado RC-552
May 8, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideLuis Ontiveros RC-231
May 8, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideAndre Pickett RC-412
May 8, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillWorking sideKelly Boudreaux RC-350
May 8, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- CapWorking sideRonnie Pace RC-547
May 8, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideKelly Boudreaux RC-350
May 8, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
NDT results
- RTAccept
May 8, 2026, 8:00 PM · D. Halloran (ASNT II)
No recordable indications.
RT film map — clock position0 indicationsClean film — no recordable indications12123456789101112
Visual inspection (CWI)
No visual inspection recorded for this joint.
No final visual on record — API 1104 requires a visual inspection on every weld.
Coating inspection
- DFT
- 25.3 mils
- Holidays
- 0
- Surface temp
- 92°F
- Humidity
- 67%
SSPC-SP 10 near-white blast · FBE + ARO overlay