WeldGuard
All joints

J-0653

acceptedAccept
Line
LN-12
Station
391+80
Weld date
2026-05-10
Spec
24" × 0.375"

32.19833, -102.71568

Cross-check alerts

  • No CWI visual inspection recorded

    Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.

Welder passes

  1. RootDitch side
    Ray Delgado RC-501

    May 10, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  2. RootWorking side
    Curtis Vann RC-514

    May 10, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  3. Hot PassWorking side
    Ray Delgado RC-501

    May 10, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  4. Hot PassDitch side
    Curtis Vann RC-514

    May 10, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  5. FillDitch side
    Ray Delgado RC-501

    May 10, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  6. FillWorking side
    Curtis Vann RC-514

    May 10, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  7. CapWorking side
    Ray Delgado RC-501

    May 10, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  8. CapDitch side
    Curtis Vann RC-514

    May 10, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

NDT results

  • RTAccept

    May 10, 2026, 8:00 PM · P. Estrada (ASNT II)

    No recordable indications.

    RT film map — clock position0 indications
    Clean film — no recordable indications
    12123456789101112

Visual inspection (CWI)

No visual inspection recorded for this joint.

No final visual on record — API 1104 requires a visual inspection on every weld.

Coating inspection

  • AcceptMarcus Ivey5/10/2026
    DFT
    23.2 mils
    Holidays
    0
    Surface temp
    89°F
    Humidity
    59%

    SSPC-SP 10 near-white blast · FBE + ARO overlay