J-3996

acceptedAccept
Line
LN-12
Station
2397+60
Weld date
2026-06-13
Spec
24" × 0.375"

34.23756, -104.58776

No open cross-check alerts on this joint.

Welder passes

  1. RootDitch side
    Odell Rains RC-121

    Jun 13, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  2. RootWorking side
    Weston Trahan RC-133

    Jun 13, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  3. Hot PassDitch side
    Junior Escamilla RC-158

    Jun 13, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  4. Hot PassWorking side
    Ty Maldonado RC-552

    Jun 13, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  5. FillWorking side
    Shane Bergeron RC-181

    Jun 13, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  6. FillDitch side
    Shane Bergeron RC-181

    Jun 13, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  7. CapWorking side
    Ronnie Pace RC-547

    Jun 13, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  8. CapDitch side
    Kelly Boudreaux RC-350

    Jun 13, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

NDT results

  • RTAccept

    Jun 13, 2026, 8:00 PM · D. Halloran (ASNT II)

    No recordable indications.

    RT film map — clock position1 indication
    12123456789101112
    • LCLow cap1:181:24 · 0.64" · d 0.07"Call varies by inspectorCap reinforcement below flush — called for grind-out and cap re-run.

Visual inspection (CWI)

  • Final visualAcceptTravis KellermanJun 13, 2026, 10:34 AM

    API 1104

Coating inspection

No coating inspection recorded for this joint.