J-0839
acceptedAccept- Line
- LN-12
- Station
- 503+40
- Weld date
- 2026-05-12
- Spec
- 24" × 0.375"
32.31179, -102.81984
Cross-check alerts
No CWI visual inspection recorded
Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.
Welder passes
- RootWorking sideMarcus Cole RC-118
May 12, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
May 12, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideTy Maldonado RC-552
May 12, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideLuis Ontiveros RC-231
May 12, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideMarvin Doucet RC-173
May 12, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- FillWorking sideAndre Pickett RC-412
May 12, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideJesse Karr RC-455
May 12, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideAndre Pickett RC-412
May 12, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
NDT results
- RTAccept
May 12, 2026, 8:00 PM · P. Estrada (ASNT II)
No recordable indications.
RT film map — clock position0 indicationsClean film — no recordable indications12123456789101112
Visual inspection (CWI)
API 1104 · Bevel, alignment and hi-lo verified prior to root.
API 1104 · Root bead visual prior to hot pass.
No final visual on record — API 1104 requires a visual inspection on every weld.
Coating inspection
- DFT
- 21.4 mils
- Holidays
- 0
- Surface temp
- 84°F
- Humidity
- 34%
SSPC-SP 10 near-white blast · FBE + ARO overlay