WeldGuard
All joints

J-0040

repairRepair
Line
LN-12
Station
24+00
Weld date
2026-05-04
Spec
24" × 0.375"

31.82440, -102.37240

No open cross-check alerts on this joint.

Welder passes

  1. RootDitch side
    Brent Kessler RC-540

    May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  2. RootWorking side
    Dwayne Ferris RC-204

    May 4, 2026, 8:35 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  3. Hot PassWorking side
    Travis Nolan RC-307

    May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  4. Hot PassDitch side
    Luis Ontiveros RC-231

    May 4, 2026, 9:10 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  5. FillDitch side
    Ronnie Pace RC-547

    May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  6. FillWorking side
    Andre Pickett RC-412

    May 4, 2026, 9:45 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  7. CapDitch side
    Kelly Boudreaux RC-350

    May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

  8. CapWorking side
    Kelly Boudreaux RC-350

    May 4, 2026, 10:20 AM · logged by C. Ramirez (Survey)

    WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4

    4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max

  9. RepairWorking side
    Jesse Karr RC-455

    May 4, 2026, 10:30 AM · logged by C. Ramirez (Survey)

    WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G

    6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max

NDT results

  • RTRepair

    May 4, 2026, 8:00 PM · D. Halloran (ASNT II)

    Material lamination in pipe body (mill defect, not charged)

    Not charged to a welder.

    Repairable indication — grind and re-weld authorized.

    RT film map — clock position2 indications
    12123456789101112
    • SISlag inclusion3:584:08 · 1.07" · d 0.03"SI exceeds API 1104 acceptance limits — charged for re-work.
    • PORPorosity11:5611:59 · 0.29" · d 0.04"Within acceptance limits.

Visual inspection (CWI)

  • Root beadAcceptTravis KellermanMay 4, 2026, 7:30 AM

    API 1104 · Root bead visual prior to hot pass.

  • Final visualAcceptTravis KellermanMay 4, 2026, 10:32 AM

    API 1104

Coating inspection

  • AcceptRenee Alcorta5/4/2026
    DFT
    22.6 mils
    Holidays
    0
    Surface temp
    95°F
    Humidity
    70%

    SSPC-SP 10 near-white blast · FBE + ARO overlay