J-2768
acceptedAccept- Line
- LN-12
- Station
- 1660+80
- Weld date
- 2026-06-01
- Spec
- 24" × 0.375"
33.48848, -103.90008
Cross-check alerts
No CWI visual inspection recorded
Cap pass complete but no CWI visual inspection is on record - API 1104 requires a visual on every weld.
Welder passes
- RootWorking sideMarcus Cole RC-118
Jun 1, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- RootDitch sideDwayne Ferris RC-204
Jun 1, 2026, 8:35 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassWorking sideBo Kinchen RC-146
Jun 1, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- Hot PassDitch sideHector Ruiz RC-528
Jun 1, 2026, 9:10 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillDitch sideKelly Boudreaux RC-350
Jun 1, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-TI-11 Rev 1SMAW uphill 6G (fixed)E6010 / E7018-H4
4–36 in OD · wall 0.188–0.75 in · hardness 235 HV10 max
- FillWorking sideDale Whitcomb RC-533
Jun 1, 2026, 9:45 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapWorking sideMarvin Doucet RC-173
Jun 1, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
- CapDitch sideDale Whitcomb RC-533
Jun 1, 2026, 10:20 AM · logged by C. Ramirez (Survey)
WPS-1104-DH-01 Rev 2SMAW downhill 5G / 6GE6010 / E8010-G
6–36 in OD · wall 0.188–0.75 in · hardness 248 HV10 max
NDT results
- RTAccept
Jun 1, 2026, 8:00 PM · D. Halloran (ASNT II)
No recordable indications.
RT film map — clock position0 indicationsClean film — no recordable indications12123456789101112
Visual inspection (CWI)
No visual inspection recorded for this joint.
No final visual on record — API 1104 requires a visual inspection on every weld.
Coating inspection
No coating inspection recorded for this joint.